NORTH LIBERTY (KWWL) -

Improvements on North Liberty's North Ridge Trail is set to begin in early June.

The city says the project will be done in phases, and closures will occur until the work is complete and safe to reopen.

The first phase is set to begin Wednesday June 3 with the largest part of the project including widening, elevating, and resurfacing the trail between Zeller Street and Golfview Drive.

Crews expect this work to last into late July. At this same time, crews will do some week-long culvert work on a segment between Cherry and Zeller streets.

After the Zeller-Golfview work is complete, crews will move to the trail segment between Penn and Cherry streets, which is expected to last about two weeks.

Crews will complete patching and overlay work between Cherry Street and Zeller Street, which is expected to last about another two weeks.

Crews will finally resurface the segment between Golfview Drive and Forevergreen Road, which is also expected to last about two weeks.

All work is expected to last until August.

Users of the trail are asked to use caution and find alternative routes around the work. Details and updates on this and other North Liberty construction projects are available at northlibertyiowa.org/projects.